Campus progress updates

  Public
By: 
caked

University Drive roadwork

Upgrades to campus services on University Drive continues between the 4-way stop at College Drive and P3. Access to P3 and Boathouse parking continues to be via West Campus Road between 7 a.m. an 5 p.m. Monday to Friday. Please drive safely during this time and give yourself an extra few minutes in the morning.

Safety first!

All staff, students and visitors to campus are reminded to obey the posted speed limit and watch for flag people who may be directing traffic.

Safe driving is essential to eveeryone's wellbeing. 

Hatley Castle walkways

Restoration work of the brick pathways around the Castle and in the Italian Gardens continues during the month of April.  The pathways are being restored with careful consideration of the historical look, and impact on the surrounding gardens. The expected completion date is April 26.

West Campus deferred maintenance

Work around the old swimming pool and Recreation Centre continues, with upgrades to power, data, water, drainage and lighting. Please be mindful of construction trucks and workers over the next few weeks.

Parking infrastructure

The expansion of P7 (adjacent to the Sherman Jen building) and EV Charger and accessible stalls adjacent to the outdoor classroom continues with completion by the end of April.

Data services

Grant

The Grant building network upgrade is scheduled to take place on Wednesday, April 24, 2019, between 5 p.m. and midnight. During this time the Grant building network, including WiFi and phones, will be down for maintenance. The network outage for Grant will be confirmed in an email to the Grant building occupants on Tuesday, April 23, 2019.

Habitat Café tills and Grant Building podiums are scheduled for migration to the upgraded network on Friday, April 26, 2019, between 2 p.m. and 7 p.m. based on their availability.